Eikenott, Gland, Switzerland

  • Tipo de Edificio:
  • Edificios Residenciales
  • Parkings
Pantalla completa Cerrar Street View

Peikko provided an efficient construction method for Eikonott Gland. Speed and technically advanced details convinced the total contractor Losinger-Marazzi to use Peikko's Column Connection solution. Solution consisted of HPKM®-Column Shoes and HPM® Anchor Bolts which were used in oval shape columns. 

Peikko's Column Shoes were helpful in speeding up the whole construction process. Now building seems almost like a LEGO-game.

Bertrand Faucherre, Didier Bourqui

Datos del proyecto

Tamaño del poyecto:
20 000 m2
Pavimentos:
4
Empresa Constructora:
Losinger-Marazzi
Prefabricador:
Bétontec
Año de construcción:
2012
Año de finalización:
2014

Habla con expertos