Built in the heart of an active industrial area of Dubai, the Four Seasons Staff Housing project is a distinguishable building among the surrounding environment. The design’s original time and cost estimates were met by using Peikko's DELTABEAM® solution. 

 Consisting of two parallel buildings with a central connection, the H-shaped structure stands out with floor-to-floor windows built within concrete blocks. The original design featured cast-in-place concrete columns and cast-in-place post-tensioned slabs with external concrete block walls.

The design consists of precast insulated cladding panels, internal precast frames and walls, and Hollow Core Slabs with the following key features:
• Continuous insulation with no thermal breaks
• Flat slabs at cantilevers and corridors
• Fast construction
• Reduced internal finishes

In 2014, the project received Honorable Mention under the Multifamily Housing category at the prestigious PCI Awards. 

www.econstruct.ae

Leer más down-arrow.png

Datos del proyecto

Tamaño del poyecto:
21000 m2
Pavimentos:
5
Inversor:
Bright Start LLC
Empresa Constructora:
Dubai Contracting Company
Prefabricador:
e.construct
Año de construcción:
2014
Año de finalización:
2014